Q124
Select the incorrect statement.
A.
Stop or red time of a signal is the sum of go and clearance intervals for the cross flow.
B.
Go or green time of a signal is the sum of stop and clearance intervals for the cross flow.
AnswerC.
Clearance time is generally 3 to 5 seconds.
D.
The cycle length is normally 40 to 60 seconds for two phase signals.
Answer: Option B
Solution
Answer: Option B
No explanation is given for this question Let's Discuss on Board