Aptitude · Q266

Time And Work

Competitive Exams · Aptitude · question 266

Q266

Shashi can do piece of work in 20 days. Tanya is 25% more efficient than Sashi. The number of days taken by Tanya to do the same piece of work is = ?

A.
15
B.
25
C.
18
D.
16
Answer

Answer: Option D

Solution

Answer: Option D
Solution: