Q266
Shashi can do piece of work in 20 days. Tanya is 25% more efficient than Sashi. The number of days taken by Tanya to do the same piece of work is = ?
A.
15
B.
25
C.
18
D.
16
AnswerAnswer: Option D
Solution
Answer: Option D
Solution: