Statement I The critical path has been defined as the longest duration path between the first and the last nodes of a project. Statement II The duration of a project is not always the same as the duration of its critical path. Statement III The earliest start and finish times of an activity are based on the condition that every activity will not be started and finished as early as possible. Find the correct answer for given statements being correct or incorrect.

A.
Statements I and II are correct, but Statement III is not correct
B.
Statements I and III are correct, but Statement II is not correct
C.
Statement I is correct, but Statements II and III are not correct
Answer
D.
Statement II is correct, but Statements I and III are not correct

Answer: Option C

Solution

Answer: Option C