Q191
The assumption in PERT is
A.
A project will always be behind schedule, if left uncorrected
B.
Cost of project will always be more than the estimated cost, if no timely corrections are taken
C.
A project can be subdivided into a set of predictable, independent activities
AnswerD.
Activities are fixed and can't be changed
Answer: Option C
Solution
Answer: Option C
Solution:
The assumption in PERT is A project can be subdivided into a set of predictable, independent activities