The assumption in PERT is

A.
A project will always be behind schedule, if left uncorrected
B.
Cost of project will always be more than the estimated cost, if no timely corrections are taken
C.
A project can be subdivided into a set of predictable, independent activities
Answer
D.
Activities are fixed and can't be changed

Answer: Option C

Solution

Answer: Option C
Solution:
The assumption in PERT is A project can be subdivided into a set of predictable, independent activities