The Boston Big Dig project faced severe delays due to:

A.
Magma chamber discovery
B.
Sinkhole formation in karst
C.
Unexpected soft clay and utility relocations
Answer
D.
Fault displacement

Answer: Option C

Solution

Answer: Option C
Solution:
The Big Dig encountered soft clays, high groundwater levels, and urban infrastructure, necessitating extensive soil stabilization and support.