Vidyalelo
Mining Engineering · Q819

Drilling and Blasting

Engineering and GATE · Mining Engineering · question 819

Q819

The charge per hole in the blasting gallery method is . . . . . . . .

A.
7 kg
B.
5 kg
C.
4 kg
D.
3 kg
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board