Vidyalelo
Civil Engineering · Q173

Engineering Economics

Engineering and GATE · Civil Engineering · question 173

Q173

The construction estimate of a project is used by:

A.
The owner of the facility
B.
The consulting architect/engineer
C.
The contractor of the project
D.
All of these
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board