The critical path of a network represents

A.
The minimum time required for completion of project
Answer
B.
The maximum time required for completion of project
C.
Maximum cost required for completion of project
D.
Minimum cost required for completion of project

Answer: Option A

Solution

Answer: Option A
Solution:
The critical path of a network represents The minimum time required for completion of project