The essential condition for the decompression of an activity is that

A.
The project time should change due to decompression
B.
After decompression the time of an activity invariably exceeds its normal time
C.
An activity could be decompressed to the maximum extent of its normal time
Answer
D.
None of the above

Answer: Option C

Solution

Answer: Option C
Solution:
The essential condition for the decompression of an activity is that An activity could be decompressed to the maximum extent of its normal time