Civil Engineering · Q23

Tunnel Engineering

Engineering and GATE · Civil Engineering · question 23

Q23

The following operations are required for tunnelling in rocky terrain: 1.Removing the foul gases2.Marking the tunnel profile3.Setting up and drilling4.Checking misfire5.MuckingThe correct sequence is:

A.
1, 2, 3, 4, 5
B.
2, 3, 5, 4, 1
C.
4, 2, 1, 3, 5
D.
2, 3, 1, 4, 5
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board