The following statements' relate to project network. Choose the correct answer for the statements being correct or-incorrect. Statement I An activity cannot be represented by more than one arrow, but. an arrow can represent one or more activities. Statement II The activities in a critical path can be preponed or postponed.
A.
Both statements are correct
B.
Both statements are incorrect
AnswerC.
Statement II is correct, but Statement I is incorrect
D.
Statement I is correct, but Statement II is incorrect
Answer: Option B
Solution
Answer: Option B
No explanation is given for this question Let's Discuss on Board