Engineering and GATE · Civil Engineering · question 74

Q74

The form Work including the props can be removed from beams, only after

A.
3 days
B.
7 days
C.
14 days
Answer
D.
21 days

Answer: Option C

Solution

Answer: Option C
No explanation is given for this question Let's Discuss on Board