The important file in making a PERT is

A.
An event can't be accomplished until activities leading to it are completed
B.
No activity from any event can be started from preceding event till it is completed
C.
Length of arrow has nothing to do with time
D.
All of the above
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
The important file in making a PERT is
1. An event can't be accomplished until activities leading to it are completed
2. No activity from any event can be started from preceding event till it is completed
3. Length of arrow has nothing to do with time