The labour rate of pay variance can be calculated by which of the following equations?

A.
Budgeted labour costs - Actual labour costs
B.
(Standard hours - Actual hours) × Actual wage rate
C.
(Standard wage rate - Actual wage rate) × Actual hours worked
Answer
D.
(Standard wage rate - Actual wage rate) × Standard hours worked

Answer: Option C

Solution

Answer: Option C