The large negative opportunity cost value in an unused cell in a transportation table is chosen to improve the current solution because.

A.
It represents per unit cost reduction
Answer
B.
It represents per unit cost improvement
C.
It ensure no rim requirement violation
D.
None of the above

Answer: Option A

Solution

Answer: Option A
Solution:
The large negative opportunity cost value in an unused cell in a transportation table is chosen to improve the current solution because it represents per unit cost reduction.