The latest time that the event can be delayed without delaying the completion of the entire project in PERT chart is:

A.
earliest allowable time
B.
latest allowable time
Answer
C.
earliest pass
D.
latest pass
E.
None of the above

Answer: Option B

Solution

Answer: Option B
No explanation is given for this question Let's Discuss on Board