Q93
The main geological issue during the construction of the Delhi Metro was:
A.
Seismic faulting
B.
Loose sandy soil with high water table
AnswerC.
Igneous dykes
D.
Glacial moraine
Answer: Option B
Solution
Answer: Option B
Solution:
The Delhi Metro construction faced difficulties due to loose sandy soil combined with a high water table, requiring dewatering and soil stabilization techniques.