Vidyalelo
Mining Engineering · Q519

Drilling and Blasting

Engineering and GATE · Mining Engineering · question 519

Q519

The percentage of extraction of the depth of seam is 200 and width of gallery is 4.8 m.

A.
33
B.
20
C.
25
Answer
D.
40

Answer: Option C

Solution

Answer: Option C
No explanation is given for this question Let's Discuss on Board