The primary reason behind the success of the Jubilee Line Extension (London) in geotechnical terms was:

A.
Blasting techniques
B.
Segmental lining and earth pressure balance TBMs
Answer
C.
Open excavation method
D.
Dewatering systems

Answer: Option B

Solution

Answer: Option B
Solution:
The extension's success was attributed to the use of earth pressure balance TBMs and segmental linings for soft ground tunneling under sensitive structures.