The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time and tn = Most likely time)

A.
B.
C.
D.
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
The probabilistic time is given by
Where to = Optimistic time, tp = Pessimistic time and tn = Most likely time.