The reduced levels of the string at the consecutive sight rails A and B are 203.575 m, 203.475 m respectively. If the difference of their R.D.s is 10 m, the gradient of the sewer line is

A.
1 in 100 upward
B.
1 in 500 upward
C.
1 in 100 downward
Answer
D.
1 in 503 upward

Answer: Option C

Solution

Answer: Option C
No explanation is given for this question Let's Discuss on Board