The settling velocity of the particles larger than 0.06 mm in a settling tank of depth 2.4 is 0.33 m per sec. The detention period recommended for the tank, is

A.
30 minutes
B.
1 hour
C.
1 hour and 30 minutes
D.
2 hours
Answer

Answer: Option D

Solution

Answer: Option D