The Standard Penetration Test is carried out at intervals of:

A.
1.5 m
Answer
B.
0.5 m
C.
2.0 m
D.
3.0 m

Answer: Option A

Solution

Answer: Option A
Solution:
The SPT is commonly performed at regular intervals of 1.5 meters or at changes in strata to evaluate soil consistency.