The technique for establishing and maintaining priorities among the various jobs of any project is known as

A.
Event flow scheduling technique
B.
Critical ratio scheduling
Answer
C.
Slotting technique for scheduling
D.
Short interval scheduling

Answer: Option B

Solution

Answer: Option B
Solution:
The critical ratio (CR) is calculated by dividing the time remaining until a job's due date by the total shop time remaining for the job, which is defined as the setup, processing, move, and expected waiting times of all remaining operations, including the operation being scheduled.