The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as

A.
Duration
B.
Total float
C.
Free float
Answer
D.
Interfering float

Answer: Option C

Solution

Answer: Option C
Solution:
Free Float is the amount of time that an activity can be delayed without delaying the early start date of any successor activity.