Vidyalelo
Mechanical Engineering · Q47

Industrial Engineering And Production Management

Engineering and GATE · Mechanical Engineering · question 47

Q47

The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode

A.
Early finish
Answer
B.
Early start
C.
Late start
D.
Late finish

Answer: Option A

Solution

Answer: Option A
Solution:
The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode Early finish