Q47
The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode
A.
Early finish
AnswerB.
Early start
C.
Late start
D.
Late finish
Answer: Option A
Solution
Answer: Option A
Solution:
The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode Early finish