The time which results in the least possible direct cost of an activity is known as

A.
Normal time
B.
Slow time
Answer
C.
Crash time
D.
Standard time

Answer: Option B

Solution

Answer: Option B
Solution:
The time which results in the least possible direct cost of an activity is known as slow time