Vidyalelo
Mining Engineering · Q124

Opencast Mining

Engineering and GATE · Mining Engineering · question 124

Q124

The value of ore is Rs. 600 per ton, production cost Rs. 400 per ton and cost of over burden removal is Rs. 50 per m3, the break even stripping ratio in m3/ton is

A.
4 : 1
B.
1 : 3
Answer
C.
3 : 1
D.
1 : 4

Answer: Option B

Solution

Answer: Option B
No explanation is given for this question Let's Discuss on Board