To complete a piece of work A and B take 8 days, B and C 12 days. A, B and C take 6 days. A and C will take :

A.
7 Days
B.
7.5 Days
C.
8 Days
Answer
D.
8.5 Days

Answer: Option C

Solution

Answer: Option C
Solution:
Given (A+B)'s one day's work =
(B + C)'s one day's work =
(A + B + C) 's 1 day's work =

Work done by A, alone= (A + B + C) 's 1 day's work - (B + C)'s one day's work

Work done by C, alone = (A + B + C) 's 1 day's work - (A + B)'s one day’s work

⇒ (A + C)’s one day’s work

⇒ (A + C) will take 8 days to complete the work together