Q8
To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?
A.
30 days
AnswerB.
35 days
C.
40 days
D.
45 days
Answer: Option A
Solution
Answer: Option A
Solution:
B alone can complete the work in