What is the function of a cutoff wall in dam construction?

A.
Improve aesthetics
B.
Drain water from reservoir
C.
Control seepage under the dam
Answer
D.
Support abutments

Answer: Option C

Solution

Answer: Option C
Solution:
A cutoff wall is built beneath a dam to prevent seepage through the foundation, reducing erosion and failure risk.