Vidyalelo
Civil Engineering · Q90

Engineering Economics

Engineering and GATE · Civil Engineering · question 90

Q90

What is the present worth of two P 100 payments at the end of the third year and fourth year? The annual interest rate is 8%.

A.
P 150.56
B.
P 152.88
Answer
C.
P 153.89
D.
P 151.09

Answer: Option B

Solution

Answer: Option B
No explanation is given for this question Let's Discuss on Board