What major geological factor delayed the construction of the Boston Big Dig project?

A.
Ground freezing
B.
Bouldery till deposits
C.
High groundwater levels and soft clay
Answer
D.
Lava flows

Answer: Option C

Solution

Answer: Option C
Solution:
The Boston Big Dig encountered significant delays due to soft clay and high groundwater levels. Extensive dewatering, ground improvement, and monitoring systems were implemented to control settlements.