Vidyalelo
Mining Engineering · Q250

Mine Legislation and General Safety

Engineering and GATE · Mining Engineering · question 250

Q250

What should be the minimum average output of an underground mine, where the manager must have First Class Managership certificate of competency?

A.
600 t/month
B.
1500 t/month
C.
2500 t/month
Answer
D.
5000 t/month

Answer: Option C

Solution

Answer: Option C
No explanation is given for this question Let's Discuss on Board