Q124
What technique was used in the Palm Jumeirah project to stabilize reclaimed land?
A.
Deep foundation piles
B.
Vibro-compaction
AnswerC.
Soil freezing
D.
Rock anchors
Answer: Option B
Solution
Answer: Option B
Solution:
Vibro-compaction was used to densify loose sand deposits, improving bearing capacity and reducing settlement on this artificial island.