Vidyalelo
Geological Engineering · Q124

Case Studies and Applied Geological Engineering Projects

Engineering and GATE · Geological Engineering · question 124

Q124

What technique was used in the Palm Jumeirah project to stabilize reclaimed land?

A.
Deep foundation piles
B.
Vibro-compaction
Answer
C.
Soil freezing
D.
Rock anchors

Answer: Option B

Solution

Answer: Option B
Solution:
Vibro-compaction was used to densify loose sand deposits, improving bearing capacity and reducing settlement on this artificial island.