Vidyalelo
Geological Engineering · Q19

Case Studies and Applied Geological Engineering Projects

Engineering and GATE · Geological Engineering · question 19

Q19

What was the main cause of tunnel face collapse in the Heathrow Express Rail Link project?

A.
Water ingress into clay
B.
Lack of grouting
C.
Excavation in London clay without support
Answer
D.
Overcutting

Answer: Option C

Solution

Answer: Option C
Solution:
The collapse occurred due to unsupported excavation in London clay, leading to loss of face stability. It emphasized the importance of real-time monitoring and pre-support measures.