What was the major geological issue in the Chunnel (Channel Tunnel) project?

A.
Water ingress in chalk marl
Answer
B.
Rockburst
C.
Thermal cracking
D.
Fault slip zones

Answer: Option A

Solution

Answer: Option A
Solution:
The Channel Tunnel passed through chalk marl, which presented groundwater control issues. Pressurized TBMs and sealing techniques were used to handle water ingress.