Q391
Whether in a suit for specific performance of contract to transfer immovable property, burden of proof is on the plaintiff to prove that the breach of contract can not be adequately relieved by compensation in money?
A.
Yes
B.
No
AnswerC.
Discretion of the court
D.
None of the above
Answer: Option B
Solution
Answer: Option B
No explanation is given for this question Let's Discuss on Board