Q285
Which combination of the following two statements (A) and (R) is correct? Assertion (A): The IRR of a project is the discount rate which reducesits NPV to zero. Reason (R): A project is worth accepting if the IRR exceeds the cost of capital.
A.
(A) is right, but (R) is wrong
B.
Both (A) and (R) are correct
AnswerC.
(A) is wrong, but (R) is correct
D.
Both (A) and (R) are wrong
Answer: Option B
Solution
Answer: Option B
No explanation is given for this question Let's Discuss on Board