Geological Engineering · Q106

Case Studies and Applied Geological Engineering Projects

Engineering and GATE · Geological Engineering · question 106

Q106

Which construction project faced tunneling challenges due to swelling clay (montmorillonite)?

A.
Channel Tunnel
Answer
B.
Panama Canal
C.
Heathrow Terminal 5
D.
Brenner Base Tunnel

Answer: Option A

Solution

Answer: Option A
Solution:
The Channel Tunnel encountered swelling clays like montmorillonite, which absorbed water and expanded, causing stress on tunnel linings.