Vidyalelo
Geological Engineering · Q13

Case Studies and Applied Geological Engineering Projects

Engineering and GATE · Geological Engineering · question 13

Q13

Which geological technique was used in tunneling for Metro Rail projects in Delhi?

A.
Cut and cover with blasting
B.
Slurry shield Tunnel Boring Machine
Answer
C.
Open-pit excavation
D.
Jet grouting

Answer: Option B

Solution

Answer: Option B
Solution:
The slurry shield TBM was used to handle soft soils and high groundwater pressure in Delhi Metro construction. This method prevents face collapse and reduces surface settlement.