Vidyalelo
Geological Engineering · Q184

Case Studies and Applied Geological Engineering Projects

Engineering and GATE · Geological Engineering · question 184

Q184

Which Indian project required rock bolting and shotcrete to stabilize hill slopes near roadways?

A.
Yamuna Expressway
B.
Rohtang Tunnel
C.
Mumbai Coastal Road
D.
Char Dham Road Project
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
The Char Dham Road Project passes through geologically weak Himalayan terrain. Rock bolting and shotcrete are employed extensively to stabilize rock cuttings and prevent landslides.