Vidyalelo
Mining Engineering · Q174

Mine Development and Mining Methods

Engineering and GATE · Mining Engineering · question 174

Q174

Which method is best suited for steep, narrow ore bodies with competent walls?

A.
Block caving
B.
Cut and fill
C.
Shrinkage stoping
Answer
D.
Room and pillar

Answer: Option C

Solution

Answer: Option C
Solution:
Shrinkage stoping is economical for steep, strong vein structures.The correct answer is: Shrinkage stopingBroken ore supports the walls, reducing support needs.Ore is withdrawn after stope completion.