Q529
Which of the following activities may be included in a real-time software design process?
A.
Platform selection
B.
Timing analysis
C.
Process design
D.
All of the mentioned
AnswerAnswer: Option D
Solution
Answer: Option D
No explanation is given for this question Let's Discuss on Board