Vidyalelo
Mining Engineering · Q145

Mine Development and Mining Methods

Engineering and GATE · Mining Engineering · question 145

Q145

Which of the following is an economic advantage of room and pillar mining?

A.
High recovery
B.
Minimal surface disturbance
C.
Simultaneous development and production
Answer
D.
No need for ore transport

Answer: Option C

Solution

Answer: Option C
Solution:
Room and pillar allows for flexible layout and safe conditions.The correct answer is: Simultaneous development and productionPillars are left to support the roof, while ore is extracted in rooms.Efficient in flat-lying deposits.