Vidyalelo
Computer Science · Q461

Software Engineering

Engineering and GATE · Computer Science · question 461

Q461

Which of the following is not a change management process?

A.
Log the changes
B.
Estimate impact on effort and schedule
C.
Review impact with stakeholders
D.
None of the mentioned
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board