Q116
Which of the following statement is correct?
A.
When slack of an activity is zero, it falls only on critical path
B.
CPM technique is useful to minimize the direct and indirect expenses
C.
Critical path of a net work represents the minimum time required for completion of project
D.
All of the above
AnswerAnswer: Option D
Solution
Answer: Option D
Solution:
- When slack of an activity is zero, it falls only on critical path.- CPM technique is useful to minimize the direct and indirect expenses.
- Critical path of a net work represents the minimum time required for completion of project.