Vidyalelo
Computer Science · Q218

System Analysis And Design

Engineering and GATE · Computer Science · question 218

Q218

Which of the following systems implementation approaches should be used if you want to run the old system and the new system at the same time for a specified period?

A.
direct
B.
pilot
C.
phased
D.
parallel
Answer
E.
None of the above

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board