Which of the following was a geological risk in the construction of the Burj Khalifa?

A.
Expansive clay
B.
Liquefiable sands
C.
Saline groundwater
Answer
D.
Collapsible soil

Answer: Option C

Solution

Answer: Option C
Solution:
Saline groundwater in the Dubai region posed challenges for foundation corrosion. Advanced concrete mix designs and waterproofing were used to mitigate these effects.