Which one of the following is assumed for timing the activities in PERT network?

A.
α distribution
B.
β distribution
C.
Binomial distribution
Answer
D.
Erlangen distribution

Answer: Option C

Solution

Answer: Option C
No explanation is given for this question Let's Discuss on Board